Friday, February 5, 2021

High Speed Rail (HSR) Jakarta - Bandung has completed 63.9%


Project name: Jakarta-Bandung High-speed Railway, Indonesia


Total length: 150 km


Contractor: CREC




Jakarta-Bandung High-speed Railway is a proposed project in Indonesia, connecting the capital city of Jakarta to the textile hub of Bandung.

China have been selected by the Indonesian Government over Japan to build the country’s first fast-train rail link.

Commencing in 2016, construction on the $5.5bn project will last for three years, with completion scheduled for 2019. The project will be developed by PT Kereta Cepat Indonesia China, a joint venture formed in October 2015 between a consortium of Indonesian state-owned companies, and China Railway International.

The project will be carried out on a business-to-business basis, with Indonesia having 60% interest in the joint venture, while China has 40%.



Railway developer PT Kereta Cepat Indonesia China (KCIC) completed tunnelling on the 1.8km Tunnel 1 beneath the Jakarta – Cikampek toll road on December 15, The Jakarta Post reports. The tunnel is the fifth to be completed, KCIC president, Mr Chandra Dwiputra, said in a statement.

“With this tunnel completion, our tunnel drilling work progress has reached 74.94% of the total tunnel length of 16km,” he says. KCIC is planning to complete two more tunnels over the next two months.


The 350km/h line is included in the government’s national strategic projects (PSN), and will serve four main stations: Halim in Jakarta, Karawang in West Java, and Walini and Tegaluar in Bandung. The Jakarta – Bandung journey time will be cut from three hours to 45 minutes.

The project has faced a number of issues during construction. The Public Works and Housing Ministry halting work for two weeks after drainage problems caused flooding on the Jakarta – Cikampek toll road. The project has also faced land acquisition issues.

Indonesia’s president, Mr Joko Widodo, had planned to combine the Chinese-led project with the Japanese-led Jakarta – Surabaya project in order to stem the projects prolonged delays and budget overruns.

KCIC has moved back the completion date to the second half of 2021 from the initial target of June 2021, which was already two years later than the original date.

IRJ, 30 Dec, 2020


Photo Jakarta Post


READ ALSO : LRT KJ 17 ABDULLAH HUKUM


No comments:

Post a Comment

MRT PY06 Sri Damansara Barat More Park N Ride Facilities

MRT PY06 Sri Damansara Barat is a one of station under MRT Putrajaya Line. Started its operation in 16th June 2022, the extension of MRT lin...